Realizations

Production of concrete for the implementation of bridge structures at the construction of the S61 Via Balticaexpressway running from Warsaw to Tallinn in Estonia

Finished
Implementation

Conpol sp. z o. o

Date

2nd quarter 2020 - 2nd quarter 2021

Execution of construction works on the E30 Kraków Mydlniki-Kraków Główny Towarowy section

Finished
Implementation

Conpol sp. z o. o

Date

3rd quarter 2018 - 1st quarter 2020

Reconstruction of track systems with accompanying infrastructure on the E59 railway line, Leszno-Czempiń section

Finished
Implementation

Conpol sp. z o. o

Date

1st quarter 2018 - 1st quarter 2020

Comprehensive upgrading and retooling of Substation 500/220/110 kV Beskudnikovo for Branch of UES FGS PAO (JSC) – Main Power Networks of the Center (MES Centra)

Finished
Investor

UES FGS PAO

Implementation

Energokomplekt OOO

Date

August 2018 - December 2019

A producer of concrete and asphalt mixtures for Strabag SA for the expansion of the national road No. 8 to the parameters of the expressway on the Radziejowice-Przeszkoda section (in 2017-2019)

Finished
Implementation

Uniwersim sp. z o. o

Date

2017 2019

Construction of a new facility for the production of DOTP with a capacity of 100 thousand tons per annum the premises of Sibur-Khimprom АО (JSC)

Finished
Investor

Sibur-Khimprom AO

Implementation

Energokomplekt OOO

Date

March 2018 - December 2018

Construction of the A1 motorway on the Tuszyn-Pyrzowice, section G

Finished
Implementation

Conpol sp. z o. o

Date

2nd quarter 2017 - 4th quarter 2018

Construction of the Szczecinek bypass along the national road No. 11

Finished
Implementation

Conpol sp. z o. o

Date

2nd quarter 2017 - 4th quarter 2018

Construction of the Maintenance Circuit of the Jawor Road at S3 along with the bridge structures

Finished
Implementation

Conpol sp. z o. o

Date

3rd quarter 2016 - 3rd quarter 2018

Reconstruction of MSDS-220 (step-down substation) on the premises of Gazpromneft-ONPZ АО (JSC)

Finished
Investor

Gazpromneft-ONPZ AO

Implementation

Energokomplekt OOO

Date

August 2016 - March 2018

OHTL 500 kV Rostovskaya NPP – Tikhoretskaya No. 2 with the expansion of Substation 500 kV Tikhoretskaya. (L=357 km) for Branch of UES FGS PAO (JSC)–Main Power Networks of the South (MES Yuga)

Finished
Investor

UES FGS PAO

Implementation

Energokomplekt OOO

Date

June 2017 - December 2017

OHTL 220 kV Komsomolskaya- Selikhino for Branch of UES FGS PAO (JSC) – Main Power Networks of the East (MES Vostoka)

Finished
Implementation

Energokomplekt OOO

Date

April 2017 - December 2017

Expansion of Substation 220 kV Vanino for Branch of UES FGS PAO (JSC) – Main Power Networks of the East (MES Vostoka)

Finished
Investor

UES FGS PAO

Implementation

Energokomplekt OOO

Date

April 2017 - December 2017

Delivery of materials for the construction of 110 kV power lines during the execution of works to connect the 110 kV PS of the Kamenskaya and Sulinskaya wind farms to the electric networks

Finished
Investor

"Ural Power Engineering Construction Company", under the contract with Sp. z o. o. "Vtoroj Vetropark FRV".

Implementation

Energokomplekt OOO

Date

April 2017 - December 2017

Construction of OHTL 220 kV Selikhino-Vanino for Branch of UES FGS PAO (JSC) – Main Power Networks of the East (MES Vostoka)

Finished
Investor

UES FGS PAO

Implementation

Energokomplekt OOO

Date

May 2016 - December 2017

Expansion and reconstruction of the Kraków-Balice Passenger Terminal

Finished
Investor

Kraków-Balice Airport

Implementation

Conpol sp. z o. o

Date

4th quarter 2013 - 4th quarter 2015

Construction of a multifunctional National Stadium in Warsaw, together with accompanying infrastructure

Finished
Investor

Alpinie Construction Polska Sp. z o. o. and Hydrobudowa Polska SA

Location

Warsaw

Implementation

RESBUD SE

Date

2008.08.28 2010.09.30 to

Execution of construction works related to the second stage of expansion of the so-fermenting hall with infrastructure in Browar Okocim in Brzesko - for Carlsberg Polska

Finished
Investor

Carlsberg Polska SA based in Warsaw

Location

Okocim Brewery in Brzesko

Implementation

RESBUD SE

Date

2008.06.30 2009.10.22 to

Construction works for a power plant Pątnów-Adamów-Konin

Finished
Investor

SNC-Lavalin Polska Sp. z o. o. 00-103 Warsaw

Location

Pątnów 62 - 510 Konin

Implementation

RESBUD SE

Date

2006.09.24 2008.09.24 to

Construction of the truck's assembly factory “Man” in Niepołomice

Finished
Investor

BILFINGER BERGER BUILDING POLSKA Sp. z o. o

Location

Niepołomice ul. Rudolf Diesel

Implementation

RESBUD SE

Date

2006.10.16 2007.08.22 to

Build-up, extension and modernization of the "P" building of the Rzeszów University of Technology

Finished
Investor

Rzeszow University of Technology

Location

Rzeszów

Implementation

RESBUD SE

Date

2000.08.01 2004.09.30 to

Construction of a Voivodeship Hospital in Przemyśl

Finished
Investor

Stand-alone Publ. Highly specialized. ZOZ in Przemyśl ul. Monte Cassino 16a

Location

Industry

Implementation

RESBUD SE

Date

1990.05.01 1999.10.30 to

Up